Investment community still skeptical over prospects for Keystone XL

Last Updated Mar 24, 2017 at 6:00 pm EDT

A yard in Gascoyne, ND., which has hundreds of kilometres of pipes stacked inside it that are supposed to go into the Keystone XL pipeline, should it ever be approved are shown shown on Wednesday April 22, 2015. U.S. President Donald Trump has given TransCanada Corp. their long awaited presidential permit for the Keystone XL pipeline, but analysts still aren't counting on it getting built. THE CANADIAN PRESS/Alex Panetta

CALGARY – The presidential permit for Keystone XL did little to assuage concerns Friday from the investment community that the project, which has stoked controversy since its inception nearly a decade ago, still faces a litany of challenges.

Beyond the political and corporate bravado that greeted the White House’s blessing, analysts took a more cautious view over whether TransCanada’s pipeline would ever get built.

“There’s still a number of hurdles,” said Justin Bouchard of Desjardins Capital Markets.

“I’m sure we’re going to see blockades like we saw with the Dakota Access Pipeline. … It’s certainly not a foregone conclusion that this thing will be built.”

Environmentalists, First Nations and others opposed to the potential climate impacts from the 1,900-kilometre pipeline say they’ll keep trying to derail it through grassroots movements — and they are warning the financial community directly.

“Investors should be very worried about the risky financials and lack of social licence attached to pipeline projects across both countries,” said Greenpeace campaigner Mike Hudema in a statement.

“The fight is far from over.”

Skirmishes could play out at the national, state and local levels as TransCanada (TSX:TRP) works to put in place the final permits needed to start construction, with Nebraska the focal point of opposition.

A state commission is considering whether Keystone XL is in Nebraska’s interest, though its review is not taking into account safety risks.

TransCanada expects that process will conclude by the end of the year and construction to begin next year, with 2020 being the earliest that crude from Alberta’s oilsands could begin flowing in the pipeline.

Robert Kwan at RBC Capital Markets said the presidential permit was widely anticipated and he isn’t including Keystone XL in his valuation of TransCanada.

There’s also the question of economics. When Keystone XL was proposed, oil prices were far above US$100 a barrel, making the case for such a pipeline more attractive.

As the pace of oilsands growth slows, Keystone XL also faces increased competition from other proposed pipelines, including Kinder Morgan’s Trans Mountain expansion, the Enbridge Line 3 replacement and TransCanada’s own Energy East Pipeline, said Bouchard.

“Four or five years ago we needed all of those projects,” he said. “Today, it doesn’t seem like we do, just given there’s been massive curtailment in spending.”

Talk of challenges facing Keystone XL — legal or political — are not surprising, said Dirk Lever at AltaCorp Capital.

“They’ll do anything to stop it,” said Lever. “They just see a pipeline like an artery coming out of the oilsands, and they want the heart to stop.”

TransCanada’s stock on the Toronto Stock Exchange barely changed Friday, closing at $61.82, up six cents or 0.1 per cent.

— With files from Dan Healing in Calgary.

Follow @ibickis on Twitter.

Latest Traffic & Weather
680 NEWS TRAFFIC @680NEWStraffic 680 News Traffic Twitter verified icon
Updated Today at 01:07 AM
CLEAR! All lanes reopened.
Latest Traffic
680 NEWS WEATHER @680NEWSweather 
Updated Yesterday at 07:46 PM
A comfortable and mild fall evening with the temperature still hovering in the low 20s! Take it all in because we…
Latest Weather